Reaching New Heights!

Tradelossa has completed the lifting and skidding of steam equipment for the Combined Cycle Project Empalme II, in Sonora. All the components were raised with a 570 metric ton Strand Jack Lifting System. Each rigging was adjusted to the dimensions of the different components for its correct positioning. The items raised were: Parts of a gas turbine,…

22 Boiler Modules!

  Tradelossa has simultaneously transported twenty-two boiler modules from Apodaca to El Carmen, Nuevo Leon. The twenty-two boiler modules ranged in size, measuring up to 27m long, 5.7m wide and 3.5m high, and weighing as heavy as 280t. The modules were transported 40km from the vendor’s facility to the project site CC Noreste using different…

Noreste Project

  Tradelossa has installed a gas generator and a set of gas turbines for the Combined Cycle Project Noreste in Nuevo Leon, Mexico. The gas generator was received in the project site, which has dimensions of 11.5 meters long x 4.1 meters wide x 4.32 high; weighing 289 tons, lifted and installed using Gantry system.…

Transformers Transportation, Mexico

  Fourteen transformers and accessories were delivered in to two different cities in Sonora, seven components were transported to Hermosillo and the rest to Ciudad Obregon. They were manufactured in Nuevo Leon, Mexico. The transformers were transported using hydraulic vehicular configurations. Once at site, the transformers were offloaded onto jacks and installed. The size of each…

Cogeneration Project, Altamira

This month we worked in the Cogeneration Project in Altamira, Tamaulipas; a combined cycle cogeneration plant which will deliver electricity and steam to the plastic production plant of a petrochemical company. We finished with the transportation and installation of a steam turbine, which dimensions were 11.2 meters long x 4.8 meters wide x 4.5 meters…

Rigging Job Ready!

These first few months have been of hard work just we finished with the installation of components for the Combined Cycle Power Plant Empalme I, in Sonora. This Project consisted in the rigging of different components with a 570 metric ton Strand Jack Lifting System. The items raised were: Parts of a steam turbine, 6.3 m (20.66…

DUBA, Salamanca Project

Delivery of three reactors for DUBA Project in Guanajuato. We conclude with the delivery of three reactors which will be used for the Clean Fuels Project for the Ultra Low Sulfur Diesel (DUBA) in Salamanca Refinery. If the pieces themselves are already striking, spectacular have been the tasks for transportation. We had to plan carefully…

1,2,3….81 Wind Blades Moved!

  Tradelossa concluded with the transportation of 81 blades, we started with this project last April, from TPI USA to Mexico, including its border crossing. During these almost seven months we have transported 81 wind components in a route of between 1,100 and 1,400 kilometers, to each park. Almost a total of 100,000 kilometers traveled…

La Jovita

Over the last 5 months we’ve worked in the project called “Baja California III La Jovita” at Ensenada, México. We’ve performed over 160 legal loads, 90 specialized transportation services and 2 oversized cargo transportations. That means the complete transportation of more than 1,000 metric tons, which had different origins, such as: Laredo (USA), Monterrey, Veracruz…

Los Ramones Pipelines

In early January, we worked in the “Los Ramones” Pipeline Project in Los Ramones, Nuevo Leon. Nearly 1,200 transport services were needed with an average of 90 kilometers per day. Each of these transports carried 4 pipelines with a diameter of 1.22 m. and 24 m of length. This project was concluded in early June.